Weekly Update: 12/27/21

With the holidays and a slightly overall smaller crew, much work continued to be accomplished this week.  Interior concrete masonry work continues in all areas of the building, primarily Classroom Areas B, and the Locker Rooms Area E.  Installation of drywall, and drywall finishing continues in Areas C & D with work now focusing on the first-floor of Classroom Area C.   Patch and rubbing of masonry walls in preparation for painting continues and will progress from Areas C & D to Area B, then to  Area E as interior masonry walls are completed.  Interior painting continues on the second-floor areas of C & D.  Installation of suspended ceiling grid has started in Area D.  Plumbing, HVAC, and electrical contractors continue with rough-in in all areas coordinating with the interior masonry work as it progresses.

122721 Observation Report.pdf