Weekly Update: 6/13/22
Paving of the NW parking lot has started.   Installation of epoxy flooring in Area F is progressing on the north half.  Installation of storefront systems continues.  Painting in the front entry and Reception is progressing.  Flooring installation in Areas C & D continues with the installation of stair treads and risers.  Mechanical, fire protection, and electrical trades continue with installation of air diffusers, sprinkler heads, light fixtures and electrical devices in ceilings as grid work is completed.  Installation of data wiring and connections continues.  Installation of electrical circuits continues in the Kitchen.

061322 Observation Report.pdf