Weekly Update: 7/18/22
Work on exterior seeding continues.  Installation of epoxy flooring in Areas B & F is progressing and will continue for the next week.  Installation of other flooring and base in Area F will continue for the next week.  Installation of bleacher seating in the performing Arts Center is complete and fixed seating is ready for installation. Installation of interior wood doors continues.  Installation of furniture continues throughout.   Mechanical, fire protection, and electrical trades continue with final installation work and start-up of HVAC systems and controls.  The State elevator inspection is complete and partial occupancy inspections are scheduled for Areas C & D.  Installation of data final connections and testing continues.