Weekly Update: 11-8-21
Overall another good weather week.  Roofing work is nearly complete except for minor detail work.  Brick veneer installation continues to progress well with about 2 ½ weeks yet to completion.  Next week, installation of brick veneer will continue as well as metal siding panels and windows.

110821 Observation Report.pdf