Weekly Update: 11/15/21
Overall another good weather week.  Exterior brick veneer installation continues to progress well with about 1 ½ weeks yet to completion.  Next week, installation of brick veneer will continue as well as metal siding panels and windows.  Installation of drywall in Area C will continue with temporary heat.  Installation of kitchen hoods and ductwork will begin as well as installation of cable trays in C & D.
 
 111521 Observation Report.pdf