Weekly Update: 4/11/22
Site grading and site clean-up continues as weather permits.   Installation of concrete work stoops at entry/exit doors continues.  Interior finish painting continues at the first-floor in Areas E & F.  Installation of epoxy flooring continues in Area A.  Installation of cabinetry, marker and tack board installation continues in Area B.  Installation of data cabling work continues.   Mechanical, fire protection, and electrical trades continue to install air diffusers, sprinkler heads and light fixtures in ceilings as grid work is completed.