PRINT ARTICLE

Print    Close This Window
Weekly Update: 4/25/22
Site concrete work continues as weather permits.   Interior drywall work continues in Areas E.  Installation of the elevator is complete. Installation of epoxy flooring continues in the Kitchen.   Installation of carpet and vinyl flooring continues in Areas C & D.   Installation of data cabling work continues.   Mechanical, fire protection, and electrical trades continue to install air diffusers, sprinkler heads and light fixtures.

042522 Observation Report.pdf