PRINT ARTICLE

Print    Close This Window
Weekly Update: 12/20/21
Much work continues to be accomplished, but with the holidays approaching, there seems to be a slightly smaller crew overall this week.  Many workers will take a little extra time away next week as well.  Interior concrete masonry work continues in all areas of the building, primarily Classroom Areas B, and the Locker Rooms Area E.   Masonry work in Areas C & D should finish this week.   Installation of drywall, and drywall finishing continues in Areas C & D with work now focusing on the first-floor areas.  Installation of metal gutters and downspouts continues.  Interior painting continues on the second-floor areas of C & D.  Installation of metal gutters and downspouts continues as well as below grade storm piping to catch basins and yard drains.  Plumbing, HVAC, and electrical contractors continue with rough-in in all areas.    coordinating with the interior masonry work as it progresses.

122021 Observation Report.pdf