Weekly Update: 12/6/21
Exterior brick veneer installation is temporarily halted due to cold weather.  Very little brickwork remains to be completed.  Fireproofing work is completed.  The building is closed in and temporary heat allows interior finish work to continue.   Next week, installation interior concrete masonry will continue as well as completing exterior brickwork.  installation of drywall systems will continue.  Block-fill and drywall prime painting will continue.  Site clean-up and removal of scaffolding will continue.
 