Weekly Update: 1/3/22
Interior concrete masonry work continues in all areas of the building, primarily Classroom Areas B, and the Kitchen and Locker Rooms Area E.   Installation of drywall, and drywall finishing continues in Area A .  Patch and rubbing of masonry walls in preparation for painting continues as masonry work is completed.  Interior painting continues on the second-floor areas of C & D.  Installation of suspended ceiling grid has started in Area D and C.   Plumbing, HVAC, and electrical contractors continue with rough-in in all areas coordinating with the interior masonry work as it progresses.