Building Updates

Below are weekly construction updates for our new school!!   If you would like to see past updates, please click the "Building Project Documents" link from the menu on the left.

Building News!

front entrance

Weekly Update: 8/1/22

Contractors continue to complete punch lists, continue final interior finish painting work, epoxy flooring in Area  F, installation of furnishings throughout, installation of wood doors, HVAC water and air balance, landscaping, and work toward project completion.  Work is progressing well toward the open house on August 21.
More +
cafeteria flooring

Weekly Update: 7/25/22

Continue to complete contractor punch lists, continue final interior finish painting work, continue epoxy flooring in Areas B & F, continue installation of furnishings throughout, complete installation of fixed seating in the Performing Arts Center, continue installation of wood doors, complete HVAC water and air balance, complete plumbing, mechanical, fire protection,  Work is progressing well toward the open house on August 21.
More +
cafeteria flooring

Weekly Update: 7/18/22

Work on exterior seeding continues.  Installation of epoxy flooring in Areas B & F is progressing and will continue for the next week.  Installation of other flooring and base in Area F will continue for the next week.  Installation of bleacher seating in the performing Arts Center is complete and fixed seating is ready for installation. Installation of interior wood doors continues.  Installation of furniture continues throughout.   Mechanical, fire protection, and electrical trades continue with final installation work and start-up of HVAC systems and controls.  The State elevator inspection is complete and partial occupancy inspections are scheduled for Areas C & D.  Installation of data final connections and testing continues.
More +
front entrance

Weekly Update: 7/11/22

Work on exterior seeding continues.  Installation of exterior post and panel signage is nearly complete.  Installation of epoxy flooring in Areas B & F is progressing and will continue for the next two weeks.  Installation of other flooring and base in Area A and F will continue for the next week or so.  Installation of bleacher seating in the performing Arts Center should be complete next week.  Installation of interior wood doors continues.  Mechanical, fire protection, and electrical trades continue with final installation work and start-up of HVAC systems and controls.  The make-up air unit for the commercial kitchen is being installed this week as well as final electrical connections to the kitchen exhaust hood.  The State elevator inspection is scheduled to be complete this week.   Installation of data final connections and testing continues.
More +
performing arts flooring nearing completion

Weekly Update: 6/13/22

Paving of the NW parking lot has started.   Installation of epoxy flooring in Area F is progressing on the north half.  Installation of storefront systems continues.  Painting in the front entry and Reception is progressing.  Flooring installation in Areas C & D continues with the installation of stair treads and risers.  Mechanical, fire protection, and electrical trades continue with installation of air diffusers, sprinkler heads, light fixtures and electrical devices in ceilings as grid work is completed.  Installation of data wiring and connections continues.  Installation of electrical circuits continues in the Kitchen.
More +
north courtyard

Weekly Update: 6/6/22

Earthworm Construction has completed final grading and compaction of the stone base for drives and parking areas.  Paving of the NW parking lot will begin on Monday.  Fine grading and topsoil placement is continuing in preparation for installation of lawns is nearly complete.  Installation of epoxy flooring in Area E corridors is complete and F has started.    Installation of storefront systems continues.  Painting of game lines and graphics in the Gym is complete.  Painting in the front entry and Reception is progressing.  Flooring installation in Areas C & D will finish next week.  Installation of overhead doors in Areas C & D is complete.  Mechanical, fire protection, and electrical trades continue with installation of air diffusers, sprinkler heads, light fixtures and electrical devices in ceilings as grid work is completed. Installation of data wiring and connections continues.  Installation of electrical circuits continues in the Kitchen.  Kitchen equipment continues to be installed.

 
More +