Skip to main content
Voice Recognition
X

Pleasant

Local Schools

Building Project

Building Updates

Below are weekly construction updates for our new school!!   If you would like to see past updates, please click the "Building Project Documents" link from the menu on the left.

Building News!

kitchen equipment being installed

Weekly Update: 5/9/22

Site concrete work continues as weather permits.   Interior drywall and painting work continues in Areas E and F.  Ceiling grid has started in the Performing Arts Center.   Installation of epoxy flooring continues in Area B and C.  Installation of carpet and vinyl flooring continues in Areas C & D, first-floor.  Installation of data cabling work continues.   Mechanical, fire protection, and electrical trades continue to install air diffusers, sprinkler heads and light fixtures.
More +
athletics entrance sidewalks complete

Weekly Update: 5/2/22

Site concrete work continues as weather permits.   Interior drywall work continues in Areas E.   Installation of epoxy flooring continues in the Kitchen.   Installation of carpet and vinyl flooring continues in Areas C & D.   Installation of data cabling work continues.   Mechanical, fire protection, and electrical trades continue to install air diffusers, sprinkler heads and light fixtures.
More +
sidewalks and curbs being installed

Weekly Update: 4/25/22

Site concrete work continues as weather permits.   Interior drywall work continues in Areas E.  Installation of the elevator is complete. Installation of epoxy flooring continues in the Kitchen.   Installation of carpet and vinyl flooring continues in Areas C & D.   Installation of data cabling work continues.   Mechanical, fire protection, and electrical trades continue to install air diffusers, sprinkler heads and light fixtures.
More +
sidewalks being poured

Weekly Update: 4/18/22

Site grading and site clean-up continues as weather permits.   Interior finish painting continues at the first-floor in Areas E & F. Installation of the elevator is progressing well.  Installation of epoxy flooring continues in Area A.  Installation of cabinetry, marker and tack board installation continues in Area B.  Installation of carpet and vinyl flooring as stared in Area D, second  floor.   Installation of data cabling work continues.   Mechanical, fire protection, and electrical trades continue to install air diffusers.
More +
sidewalks are being poured

Weekly Update: 4/11/22

Site grading and site clean-up continues as weather permits.   Installation of concrete work stoops at entry/exit doors continues.  Interior finish painting continues at the first-floor in Areas E & F.  Installation of epoxy flooring continues in Area A.  Installation of cabinetry, marker and tack board installation continues in Area B.  Installation of data cabling work continues.   Mechanical, fire protection, and electrical trades continue to install air diffusers, sprinkler heads and light fixtures in ceilings as grid work is completed.
More +
speakers being installed in gym

Weekly Update: 4/4/22

Site grading and site clean-up continues as weather permits.   Installation of concrete work stoops at entry/exit doors continues.  Interior finish painting continues at the first-floor in all Areas  and final door frame painting continues in Areas C & D.  Installation of epoxy flooring continues in Areas C & D is completed.  Installation of cabinetry, marker and tack board installation continues in Area B.  Installation of suspended ceiling grid continues in the main corridors in A and E.  Data cabling work continues.   Mechanical, fire protection, and electrical trades continue to install air diffusers, sprinkler heads and light fixtures in ceilings as grid work is completed and in preparation for upcoming above ceiling inspections in Areas A & B.
More +

New Building Renders