Skip to main content
Voice Recognition
X

Pleasant

Local Schools

Building Project

Building Updates

Below are weekly construction updates for our new school!!   If you would like to see past updates, please click the "Building Project Documents" link from the menu on the left.

Building News!

drywall almost completed

Weekly Update: 11-29-21

Exterior brick veneer installation continues to progress toward finishing with about ½ week yet to go.  Fireproofing work is nearing completion as well as window installation.  Other openings are being closed-in for weather protection.   Aluminum storefront systems will not be installed until sometime in February to avoid damage.  Next week, installation interior concrete masonry will continue, installation of drywall systems will continue and block-fill painting will start in Areas C & D.
 
More +
pipe insulation

Weekly Update: 11-22-21

Exterior brick veneer installation continues to progress well and will finish the first part of next week.  Next week, installation of metal siding panels, gutters/downspouts,  and windows.  Installation of drywall and drywall finishing will continue in Areas C & D with temporary heat.  
More +
interior hallway picture

Weekly Update: 11-15-21

Overall another good weather week.  Exterior brick veneer installation continues to progress well with about 1 ½ weeks yet to completion.  Next week, installation of brick veneer will continue as well as metal siding panels and windows.  Installation of drywall in Area C will continue with temporary heat.  Installation of kitchen hoods and ductwork will begin as well as installation of cable trays in C & D.

More +
Admin Office area brickwork

Weekly Update: 11-8-21

Overall another good weather week.  Roofing work is nearly complete except for minor detail work.  Brick veneer installation continues to progress well with about 2 ½ weeks yet to completion.  Next week, installation of brick veneer will continue as well as metal siding panels and windows.
More +
exterior building picture, windows installed

Weekly Update: 11-1-21

Overall a good weather week with a lot of progress.  Roofing work is nearly complete except for the lower canopies.  Brick veneer installation is progressing well.  Next week, installation of brick veneer will continue as well as metal siding panels and windows.
More +
interior wall contruction

Weekly Update: 10-25-21

It was a rainy week overall this week, but progress continues.  Next week, installation of the new gas service will continue, brick veneer should be complete at Area A, and brick installation will continue at Areas B & C.  Installation of metal siding panels will continue, installation of drywall in Area D will continue, brick cleaning will continue at Area C, and roofing work should be completed at Area F.
More +

New Building Renders