Work on exterior seeding continues. Installation of exterior post and panel signage is nearly complete. Installation of epoxy flooring in Areas B & F is progressing and will continue for the next two weeks. Installation of other flooring and base in Area A and F will continue for the next week or so. Installation of bleacher seating in the performing Arts Center should be complete next week. Installation of interior wood doors continues. Mechanical, fire protection, and electrical trades continue with final installation work and start-up of HVAC systems and controls. The make-up air unit for the commercial kitchen is being installed this week as well as final electrical connections to the kitchen exhaust hood. The State elevator inspection is scheduled to be complete this week. Installation of data final connections and testing continues.