Weekly Update: 11/29/21

Exterior brick veneer installation continues to progress toward finishing with about ½ week yet to go.  Fireproofing work is nearing completion as well as window installation.  Other openings are being closed-in for weather protection.   Aluminum storefront systems will not be installed until sometime in February to avoid damage.  Next week, installation interior concrete masonry will continue, installation of drywall systems will continue and block-fill painting will start in Areas C & D.
 